Rhode Enabling Infrastructure – Phase 1

SimpleViewer requires JavaScript and the Flash Player. Get Flash.

Client: Offaly County Council – North Offaly Development Fund

Value: €1.7 million

Description of Project:

M&B Construction Ltd was the Main Contractor on this project and was appointed to the role of Project Supervisor Construction Stage.

The project included the following work elements;

  • Construction of 8km of new watermains and sewers. ( Sewers from 225mm to 1050mm,  watermains range in diameter from 200mm – 300mm). Installation of sluice valves, airvalves, bulk flow watermeters and connection to Offaly County Council network.
  • Construction of reinforced insitu concrete stormwater attenuation unit.
  • Temporary and permanent road reinstatement and construction of new roads, roundabouts, kerbs, footpaths, cycleways, speed ramps, speed cushions, splitter traffic islands etc.
  • Installation of Class 1 Oil Interceptor
  • Demolition of existing structures including foundations of power station cooling towers.
  • Installation of power, telecommunication and site lighting ducting and associated chambers.